A 500kV transmission line tải bet88 be built in Quang Tri province

Nguyễn Thuấn

The Lao Bao – Quang Tri 2 Substation power transmission line expected tải bet88 help enhance grid capacity for renewable energy and prepare for electricity imports from Laos.

tải bet88

The People’s Committee of central Quang Tri province has approved the investment policy of a project building a 500kVpower transmission line between Lao Bao – Quang Tri 2 Substation.

The transmission line has a total length of 34.58km, aiming tải bet88 enhance grid capacity for renewable energy, meeting electricity transmission demand from border areas tải bet88 the province’s center, and prepare for electricity imports from Laos.

Total investment capital is estimated at over VND1.25 trillion (.8 million).

The Electricity of Vietnam (EVN) got the green light from local authorities tải bet88 become the project’s investor.

Construction is scheduled tải bet88 begin in the second quarter of 2026, with commissioning expected by the fourth quarter of 2027.