Three more bóng đá bet88 recognized for commercial operations
Plants with a total capacity of 48.8 MW granted a commercial operations date.

Three wind bóng đá bet88 plants were recognized for commercial operations in August: the Hoa Binh 1 Wind bóng đá bet88 Plant, Phase 2, and the Ninh Thuan Wind bóng đá bet88 Plants No. 5 and No. 7A, with capacity of 15.2 MW, 21 MW, and 12.6 MW, respectively.
In early August, 106 wind bóng đá bet88 plants with a total capacity of 5,655.5 MW sent documents registering for integration into the national electricity grid and testing, and seeking a commercial operations date (COD).
According to the Ministry of Industry and Trade (MoIT)’s Circular No. 02/2019/TT-BCT dated January 15, 2019 on project development and standardized bóng đá bet88 purchase agreements for wind bóng đá bet88, the seller is responsible for sending the buyer a draft of the process of commissioning and the acceptance of the bóng đá bet88 plant in accordance with the current regulations and technological standards of the wind bóng đá bet88 plant 90 days prior to the date of commercial operations.
In order to meet the deadline for submitting the application for commissioning and acceptance, and to prepare the application for COD recognition before October 31, 2021, the investor of wind bóng đá bet88 plants must send documents and dossiers to Electricity of Vietnam (EVN) no later than August 3, 2021. Thus, while 24 wind bóng đá bet88 plants have been granted a COD, the remaining plants are at risk of not being able to generate bóng đá bet88 as prescribed, given that the deadline is just over one month away.
The Vietnam Clean Energy Association and the People’s Committees of provinces that have bóng đá bet88 have therefore submitted written petitions to the Prime Minister, the MoIT, EVN, and relevant ministries and agencies seeking an extension to the timeframe for commercial power generation from three to six months.